|
|
|
Our
team has hundreds of millions of construction dollar
experience in the delivery systems described below,
each of which can be tailored to meet our client's needs.
General
Contracting Historically,
most building projects have followed a more
traditional process in which an owner hires
an architect to begin the process of developing
a design and preparing the necessary documents
to build it. An owner typically hires a general
contractor under a separate contract to construct
the facility. The architect and general contractor
are hired to act in the owner's best interest.
The architect is paid a fee for the services
he provides, and the contractor's compensation
is included in the cost of construction. Design-Bid-Build
is the most common option, with Negotiated Select
Team as an additional option. This alternative
has the same contractual relationship as Design-Bid-Build,
but the general contractor is involved much
earlier in the process to assist in determining
costs, scheduling and constructability issues
to enhance project performance.

Design-Bid-Build Although
this method is the most common method of project
delivery, it has recently been subject to more
scrutiny. This form of delivery has three phases:
(1) The owner engages an architect to design
and prepare construction documents for the project
to be used to bid the job; (2) a contractor
is selected, and submits a cost commitment;
(3) the contractor is hired to build the project.
This method is generally used in the public
sector when selecting the "low-bid"
contractor is mandated. Because no communication
exists between the architect and contractor
during the design phase, this method can be
quite time-consuming, and can result in multiple
change orders and an increase in claims, unlike
other delivery methods.


Negotiated
Team Members This
delivery method is similar to the Design-Bid-Build
method in which separate contracts exist for
design and construction, but utilizes our design-assist
services. At the inception of a project, the
owner selects an architect and a contractor,
typically based on qualifications, with whom
fees for services are negotiated. The owner,
architect and contractor work closely together
as a team from commencement of the design process.
The contractor assists the architect in the
design and documentation process by providing
scheduling, estimating, phasing and building
systems evaluation. When the project design
is complete, the final construction costs are
negotiated through bids from subcontractors,
and construction begins. This method is widely
used in the private sector, and experienced
owners, and those owners, architects and contractors
who team up together frequently. The most significant
advantages are the cooperative team approach
to the process and the accessibility of construction
expertise during the design phase of the project.
This team approach also tends to eliminate the
inherent adversarial relationships which often
occur between design and construction, and lessen
the potential for litigation. The primary disadvantage
is perceived to be the lack of competitive bidding,
and an owner's questioning whether he has the
most economical construction cost. Competitive
bidding, however, comes from the subcontractor,
supplier, and vendor marketplace, and the "open
book" approach used by Lytle Construction
Services, which assures the lowest possible
cost for the right project scope.


Design-Build Design-Build
project delivery is another form of contracting
that has been most widely received by private
owners.
Under the Design-Build format,
the owner contracts with a single entity, the
design-builder, to provide both design and construction
services. The Design-Build entity may be a single
firm or a joint-venture. The team typically
includes an architect and a contractor, where
the architect is a subcontractor of the contractor.
The principal advantages of Design-Build are
the single point of responsibility, and the
potential to remove otherwise independent phases,
thereby streamlining the process, advancing
the design and construction schedules, and saving
valuable time.
The Design-Build team
is responsible for both the design and construction
under one contract. There are two primary players:
the owner and the design-builder. This method
is the most commonly used form of design-build,
although other forms exist. Once pre-selection
materials have been prepared, the typical Design-Build
process primarily involves the design and construction
of the project. Design is completed by the architect
who is part of the LCS Design-Build team.
A
preliminary cost commitment generally is made
during the design phase in the form of a guaranteed
maximum price (GMP). This method is common for
projects that need to move quickly, and is most
effective when the project is clearly defined
at inception, but may require extensive coordination
of consultants and subcontractors.
The
principal advantages are that the single point
of responsibility minimizes the owner's risk,
reduces the opportunity for change orders, and
reduces potential construction delays.


Construction
Manager as Constructor Under
this delivery method, a CM is hired prior to
the completion of the design phase to act as
the project coordinator and general contractor.
This method is structurally and contractually
similar to Design-Bid-Build, has the advisory
benefits of CM-Advisor, and involves the early
cost commitment characteristics of Design-Build.
The CM-constructor may be hired by bid to deliver
the building for a guaranteed maximum price
(GMP) or by creating multiple bid packages.
In either case, the CM assumes all the liability
and responsibility of the general contractor.
The reasoning behind this method is often referred
to as "CM-at-Risk". This method involves
the owner, architect and construction manager.
The
process has three phases: The owner first hires
an architect to design the project. When design
is approximately 30% complete, scope-of-work
documents are prepared; the project is then
bid, based on those documents, in order to select
the CM-constructor. The owner hires the CM-constructor
to advise during pre-construction, and to build
the project. Upon completion of construction
documents, the CM-constructor generally will
rebid some or all of the construction to multi-prime
contractors or other subcontractors. This method
is best utilized for projects that need to be
fast-tracked, or for an owner for whom cost,
schedule, or construction implementation would
be difficult to manage. The primary advantage
is the initial focus on design issues and the
provision of construction advice during design,
while providing careful oversight of costs,
schedule, and constructability. For some owners,
the most important advantage is early cost definition
and schedule guarantees. Disadvantages include
the potential for adversarial relationships
and change orders/claims from low bidding prime
or trade contractors.


Design-Assist All
design and construction delivery options afford
the owners in both the public and private sectors
the correct methodology, depending on the specific
goals of the project. These goals can range
from simply being an extension of the owner's
staff to monitoring and providing oversight
of either simple or complex design and construction,
to providing early cost, schedule, and quality
guarantees of those same projects. The key to
the success of all of the delivery methods is
early involvement in the programming and design
by a qualified contracting partner, or what
we call Design-Assist services.
These
services include verification of program intent
to meet site selection needs and to validate
the project's feasibility to meet early cost
targets and schedule milestones. It also includes
preliminary budgetary services in both line
item cost estimation and building systems analyses
to provide a value-check of the project's ability
to meet funding requirements and anticipated
duration. Other services during the pre-construction
phase of the project are value-management exercises
to ensure the optimum amount of dollars spent
for the desired scope of the project, in-depth
scheduling analyses to both identify long lead-time
items critical to meeting established dates,
and to evaluate opportunities for possible schedule
improvement by overlapping certain elements
of the work for early start and fast-track capability.
We also examine the project materials and methods
to determine if assumptions made during preliminary
design can, in fact, be built economically in
the field.
This constructability review
is performed by bringing in staff from the proposed
on-site building team to work in tandem with
the design and estimating staff and obtain "buy
in" of all decisions before the project
hits the site. Our Design-Assist services combine
the latest in technological application to lessons
learned in the field. We apply common sense
thinking and planning to what can seem like
an overwhelming task when considering the design
and construction of a project.

|
|

|
| |
 |
|

|
|
|
|
©
2004, 2005 Lytle Construction Services,
LP 3941 William Penn Hwy
Murrysville, PA 15668 Phone: 724-327-2424
Fax: 724-327-1599
|
|
 |
|
|