Though Lytle Construction Services is new to the industry, its employees are seasoned professionals with years of experience in the business. Working with their former employers, personnel now employed by Lytle Construction Services had significant involvement in each building pictured in this project gallery.


Quantum One Office Building
Quantum One
Pittsburgh, PA

  • Design / Build
  • Completed 04/01
  • 4-story steel structure
  • $12,000,000
  • 160,00 SF
  • Landscaped grounds

This project included significant planning, constructability reviews and value engineering.  It includes office space, a fitness center, coffee shop and a two-story lobby.


Soffer D1A Retail Building
Soffer D1A
Pittsburgh, PA

  • CM at Risk
  • 41,040 SF
  • Office, retail and restaurant space
  • $2,500,00
  • Completed 10/02
  • 3-story building

This project included construction management and general services for a building with retail and restaurant facilities on the ground floor.  The second and third floors house office space.


Alcoa Business Service Center
Alcoa Business Services Center
Pittsburgh, PA

  • CM at Risk
  • 228,000 SF
  • 1-story garage underground
  • $26,000,000
  • Completed 12/02

This project included a tenant fit-out on the fourth, fifth and sixth floors.  The fit-out work consisted of installing a raised floor system for Alcoa's data communications systems.


Health America Building
HealthAmerica
West Mifflin, PA

  • GC
  • 26,000 SF
  • Completed 1995
  • Part of 46,000 SF development

This complete turnkey project required interfacing with various governmental agencies for access to a major state highway.  The building was constructed in nine months.


 

Greater Pittsburgh Community Food Bank
Greater Pittsburgh Community Food Bank
Duquesne, PA

  • CM
  • Completed 12/99
  • 96,000 SF
  • Award Winner
  • $5,000,000
  • 25' high freezers and coolers

This food distribution center won the Three rivers Environmental Award and a LEED Silver Rating for its green and sustainable aspects.  It was completed on budget and a month ahead of schedule.


Kinkos Retail Space
Kinko's
West Mifflin, PA

  • GC
  • Completed 1995
  • Structure built in 7 months
  • 13,000 SF
  • Access roads to a state highway

This 13,000 SF turnkey project included site development and required interfacing with various governmental agencies for access onto a major State Highway. This structure was one part of an entire site development including access roads as well as two other buildings. Total square footage of rentable space on this site is 13,000 SF. Kinko's Retail Space was constructed in seven months.


 

West Mifflin goodyear Tire Center
Goodyear Tire Center
West Mifflin, PA

  • GC
  • 5,000 SF
  • Project completed in four months
  • Completed 12/94
  • Turnkey project

This project included site development and required interfacing with various governmental agencies for access onto a major state highway.  The structure was part of a larger 46,000 SF development.


 

West Mifflin Applebees Restaurant
Applebee's
West Mifflin, PA

  • GC
  • Completed 12/94
  • Project completed in six months
  • $750,000
  • 5,000 SF

This facility included site development and required interfacing with governmental agencies for access to a major state highway.  The project was constructed in six months.


Miracle Mile Shopping Center
Miracle Mile Shopping Center
Monroeville, PA

  • GC
  • Completed in six months
  • 1,700 LF renovation

Facade removal and renovation performed during normal business hours allowed tenants to remain open. Renovations included the installation of new structural steel, glass curtainwall, and EIFS construction.


Holiday Centre
Holiday Centre
Monroeville, PA

  • GC
  • Completed in seven months
  • Over 250,000 SF retail space

Strip center has two anchor tenants. Site work included 1000 CY of rock removal. Construction was completed in seven months despite site constraints. Façade consisted of concrete, FRP column covers, EIFS, and metal roof canopies.


Corporate One West
Corporate One West
Bridgeville, PA

  • GC
  • Completed in nine months
  • 45,000 SF

This facility was built for mixed-usage tenants. The structural steel frame supports a mix of materials including glass curtainwall and cedar. The fireplaces significantly enhance the third floor tenant space.


Plaza on Mall Boulevard
Plaza On Mall Boulevard
Monroeville, PA

  • GC
  • Completed in seven months
  • 54,000 SF retail space

The scope of work for this strip center was comprised of a masonry load-bearing curtainwall, structural steel frame, approximately 300 LF of glass storefront, sign band and a canopy comprised of rolled sheet metal.


 

Enterprise Bank
Enterprise Bank
Allison Park, PA

  • Design/Build
  • Cost: $1,600,000
  • 11,000 SF

Acting as design and builders, LCS' Limited Partners erected a two-story commercial banking center.  During the second phase, an additional floor was build to house offices, meeting rooms, board rooms and a break area.


Pitt Upper Campus Housing
Pitt Upper Campus Housing
Oakland, PA

  • CM at Risk
  • Cost: $16,000,000
  • 130,000 SF

This project took 11 months to complete and included dormitory space, as well as student common areas. Its construction consisted of a masonry-bearing curtainwall utilizing pre-cast planks for the floor system.


 

Forbes Tower
Forbes Tower
Oakland, PA

  • CM at Risk
  • Completed in 24 months
  • 250,000 SF Tower
  • 272,000 SF Garage

This 11-story mixed-use facility was built for the University of Pittsburgh and UPMC. The tower includes office space, classrooms and a computer lab. Beneath the tower lies a 3-story, concrete underground parking garage. 


 

Blue Cross/Highmark Patient Center
Blue Cross/Highmark Patient Center
Greentree, PA

  • GC
  • Completed in 11 months
  • 50,000 SF
  • Cost: $7,000,000

This premier healthcare facility included doctors's offices, examination rooms, physical therapy center, and outpatient clinic. This structure was a prototype for four other regional facilities, and was completed in 11 months. 

   
 